The Staythorpe Battery Energy Storage System (BESS) is one of the UK’s largest energy storage projects and a vital step towards a more secure, flexible, and low-carbon energy future
Now under construction near Staythorpe Power Station in Nottinghamshire, this nationally significant development will strengthen the UK’s electricity grid by storing renewable energy at scale, helping ensure that clean power is available exactly when it’s needed.
This hub is here to keep you, our neighbours and community partners, informed, involved, and connected throughout the project. You’ll find updates, key contacts, events, and details about how we’re working to deliver lasting local benefits.
Powering a sustainable future
Community relations programme
Build trust
Provide clarity
Create local value
Build trust
Build trust
We know that major infrastructure projects must earn the trust of the communities that host them. That’s why we’ve committed to open communication, local presence, and a named team who are here to listen and respond. From our first community meeting through construction and into operation, we aim to build relationships based on honesty, respect, and shared understanding.
Provide clarity
Provide clarity
Clarity means no surprises. We’re committed to sharing accurate, timely information throughout construction and beyond, including what’s happening, when, and why. Our Community Hub, newsletters, signage and on-site teams are all designed to make it easy for local residents to get answers, find updates, and see how the project is progressing.
Create local value
Create local value
The Staythorpe BESS isn’t just about clean energy, it’s about delivering lasting value to the local area. From biodiversity improvements, school workshops to our Community Benefit Scheme, our goal is to leave a positive legacy.
Updates
Here’s where we post updates on communications and construction site activity information.
Footpath access update: works near Staythorpe Road entrance 27.08.2026
Residents are advised that upcoming 11kV connection works will take place near the entrance to the Public Right of Way (PRoW) and permissive footpath at the Staythorpe Road end.
To ensure the safety of both the public and the workforce, additional temporary fencing may be required while these works are carried out. Access for pedestrians will remain available at all times, with a minimum 1.2 metre-wide walkway maintained in line with highway requirements.
We will continue to monitor the area and aim to keep any inconvenience to a minimum.
Temporary traffic management and equipment deliveries: 17.08.2026
Temporary traffic management will be in place with single lane traffic between September 1-16 due to civil works associated with utility installation. The road will remain partially open throughout.
Electrical equipment delivery is also expected to start from the beginning of September.
Road closures and equipment deliveries – early September: 04.08.2026
As construction progresses, we’re planning a short-term road closure in the vicinity of the site in early September to allow works on the 11kV cable connection and the water main connection to site. The works will take place in early September, with an exact date yet to be confirmed – we will update this page, and notify residents directly, around two weeks before the closure begins.
Residents can also expect a temporary increase in delivery vehicles to the site during early to mid-September as further equipment arrives. All deliveries will continue to operate within the agreed hours set out in the Construction Traffic Management Plan, and we will keep monitoring this to minimise disruption to the local area.
Transition to electrical works: 17.07.2026
Construction on site is moving into its next phase, with work transitioning from civil engineering to electrical installation.
This is a planned and expected part of the programme. As electrical works ramp up, site staffing numbers will increase by the end of July 2026, within the levels previously agreed with Newark and Sherwood District Council and Nottinghamshire County Council.
Residents may notice a modest increase in vehicle movements to and from site as a result of the additional workforce. All site traffic will continue to operate within agreed hours and routes, and we will keep monitoring this to minimise disruption to the local area.
Enhanced site security measures - security guards and dogs: 01.06.2026
We have introduced additional security provisions in response to a recent theft incident at a nearby energy site, in which copper was stolen.
Copper theft is a known risk across the construction and energy sectors. Incidents of this kind can cause direct financial loss, but they also carry programme risk. Replacement materials for specialist electrical components can have long lead times, and any resulting delays have a direct impact on construction activity and delivery timelines.
In response, two trained security guards with dogs are now on site at all times outside of construction hours. This is in addition to existing site security measures.
We want local residents and the wider community to be aware of this. An increased security presence helps protect the site and its materials, but it also acts as a visible deterrent to opportunistic activity in the surrounding area. If you notice anything suspicious near the site or in the local area, please contact the police on 101 or report it online at www.nottinghamshire.police.uk
Permanent fencing works: 18.05.2026
Permanent fencing works are to commence from Monday 18th May.
Permissive path and existing footpath (FP1) closures: 22.04.2026 - 08.11.2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
To ensure continued access where possible, the closures will be staggered between the existing footpath and the permissive path. However, overhead powerline diversion works will require temporary closures of each route at different times where they intersect.
The closure dates are as follows:
Permissive Path Closure: 22 April 2026 to 6 May 2026
Existing Footpath (FP1) Closure: 6 May 2026 to 8 November 2026
These measures are in place to prevent and mitigate any risk of accidents during the construction works. We apologise for any inconvenience caused and thank you for your understanding.
Public footpath FP1 update: 20.03.26
Following a recent incident in which safety fencing was dismantled, the fencing along this section of Public Footpath FP1 has now been fully reinstated. Anti-tamper fixings have also been installed, and CCTV is in operation.
The fencing is in place as a necessary health and safety measure during the construction phase, protecting members of the public from areas where there are changes in ground levels and active construction activity.
We have worked closely with the local authority and our contractors to keep this section of Public Footpath FP1 open safely for as much of the construction period as possible, recognising its importance to local users.
We kindly ask all users to respect the safety measures in place. Interference with fencing or other site infrastructure can create unnecessary risks for both the public and site workers.
If safety measures continue to be interfered with, we may need to review whether it is possible to safely keep this section of FP1 open during construction. This could require an application to Nottinghamshire County Council to temporarily close this section of the footpath and rely on the existing diversion route for the remainder of the works.
We thank the many members of the community who continue to use the footpath responsibly and engage respectfully with workers on site, helping to ensure the route can remain open safely during the construction period. The safety of the public and our workforce remains our priority.
Traffic monitoring and transparency update: 05.03.26
We are aware that, since construction began at the Staythorpe BESS site, vehicles have at times been observed using or entering the site access outside of the project’s permitted delivery hours.
For clarity, all authorised Staythorpe BESS construction deliveries are strictly limited to 9:00am to 4:00pm, Monday to Friday, in accordance with the approved Construction Traffic Management Plan agreed with the Local Planning Authority.
Vehicle movements outside of these hours are not associated with the Staythorpe BESS project unless explicitly confirmed otherwise.
While site activity has been monitored from the outset, we recognise that some vehicle movements in the wider area may have caused uncertainty. To ensure clarity, we are now formally recording and publishing a log of vehicle movements identified as not related to the Staythorpe BESS works.
This log will be updated on a rolling basis and is intended to provide a clear, factual record distinguishing authorised project traffic from unrelated activity in the area.
We remain committed to operating in full compliance with our approved planning conditions and to providing transparent updates to the local community.
Pile level correction (Commencing late March and scheduled to conclude late May 2026)
Pile trimming to correct levels using Stihl sawing methods.
Works planned and sequenced to minimise duration and overall disturbance.
A gravity-fed water suppression system will be deployed throughout to control dust emissions.
Noise monitoring will continue in line with the Best Practicable Means (BPM) as defined under BS 5228.
Q1 2026 activities
Overhead line diversion
Piling Works (Scheduled to conclude mid March 2026)
The contractor is applying Best Practicable Means (BPM) as defined under BS 5228.
Continuous vibration monitoring during piling operations.
Mobile noise monitoring ongoing, with fixed noise monitoring stations operational.
Decibel levels recorded at agreed receptor locations throughout the day.
Piling hours voluntarily restricted to 08:00–16:00, including a mandatory one-hour shutdown at lunchtime to provide respite.
Non-metallic resilient dolly fitted to the rig and regularly inspected to minimise impact (eliminating metal-on-metal contact).
Temporary closure of footpath (FP1) at Staythorpe: 09/10/2025
A six-month temporary closure of Public Right of Way Footpath FP1 has been approved by Nottinghamshire County Council. This closure is necessary to support safe construction works and infrastructure installation.
The notice has been displayed in a visible location near the entrance to the footpath.
During the period of restriction there is a signed, permissive alternative route for pedestrians.
Powering a sustainable future
Staythorpe BESS Community Relations Programme
We are committed to building trust and delivering long-term value to the communities surrounding the Staythorpe BESS project. Our Community Relations Programme sets out how we will communicate clearly, minimise disruption, and involve local people at every stage.
Clear communication
Named local contacts from both Elements Green (Developer) and Mitie (Principle Contractor)
All enquiries acknowledged within three working days
Transparent complaints process with clear escalation routes
Respect during construction
Public notice of high-traffic days and deliveries
Published working hours with noise and dust mitigation protocols
Banksman in place to manage any necessary footpath or crossing interactions
Accessible information
Online Community Hub: elementsgreen.com/StaythorpeBESS
Regular updates, FAQs, and event details
Printed posters and notices in key locations with QR code access
Email updates available by sign-up
Transparency on Benefits
Local job and supplier opportunities promoted and tracked
Clear biodiversity commitments including 12 acres of woodland and wildflower meadow, and over 120 new trees
Details of the Community Benefit Fund has been shared with the Averham, Kelham and Staythorpe Parish Council. Final arrangements will be shared once agreed.
Email updates available by sign-up
In-Person Engagement
Meet-the-Team events starting 19 August 2025
Drop-in format with project visuals and timeline displays
Project at a glance
Project overview
Approved: 2024
Capacity: Peak Power 360MW | Storage 720MWh — enough to power over 95,000 homes for a full day
Lifespan: 40 years
Construction & delivery
Timeline: On-site works commenced in 2025; operational by mid-2027
Jobs created: Approx. 60 during construction
Partnerships: In February 2025, Elements Green signed a £71.5M contract with Mitie Power & Grid (via G2 Energy) to lead design and construction — combining deep expertise in energy storage, infrastructure, and community delivery.
Environmental & national impact
Biodiversity Net Gain: 25.7%
Includes 12 acres of new woodland and wildflower meadow, plus 120+ trees planted
National Significance: Staythorpe BESS supports the UK Government’s clean energy goals, strengthening grid resilience, creating skilled green jobs, and reducing reliance on fossil fuels.
Future-Focused: A key part of the UK’s smart energy infrastructure, where energy storage is the backbone of a net-zero future.
The Staythorpe BESS project has been developed with long-term planning, rigorous environmental assessment, and community consultation at its core. This timeline outlines the key milestones from early feasibility to final construction — and sets the stage for the project’s operation and legacy over the decades to come.
As we move forward, we remain committed to keeping the local community informed, involved, and updated every step of the way.
2021
Initial site search and feasibility studies conducted.
2022
Project design and assessment phase commenced.
Q3: Planning application for the BESS submitted to Newark and Sherwood District Council.
2023
(June-July): Public consultation period for the project’s proposals.
2024
Elements Green secures full planning permission for the 360MW/720MWh Staythorpe BESS from the Planning Inspectorate.
2025
(February): Elements Green signs a £71.5 million deal with Mitie, appointing G2 Energy (part of Mitie Power & Grid) as the Principal Designer and Principal Contractor for the project, including the associated 400kV grid connection infrastructure.
(July): Elements Green secures £140 million debt facility from Goldman Sachs Alternatives for the project and construction work starts on the site.
(July): HiTHIUM chosen to supply 5MWh BESS DC blocks along with fully customied integration solutions.
(August) RES chosen to operate Staythorpe once operational – Given O&M contract – Operation and Maintenance Agreement.
2026
Ongoing construction, including arrival of Transformer, Batteries and Power Control Systems.
2027 and beyond
(Mid 2027): Expected completion and full commissioning of the project, including the 400kV grid connection infrastructure.
Partnering with Elements Green, RES manage the Staythorpe Battery Energy Storage System – Once operational, itwill be one of Europe’s largest grid-scale battery storage assets, helping deliver reliable, flexible, and zero-emissions energy to the UK.
Powering a sustainable future
Frequently asked questions
What is a Battery Energy Storage System (BESS)?
A BESS stores electricity like a large rechargeable battery, helping to balance the grid by storing intermittent renewable energy for use when consumer demand is high.
Why was Staythorpe chosen?
The site sits right next to the National Grid’s Staythorpe Substation where this kind of project can connect efficiently into the high-voltage network with minimum additional Grid infrastructure requirements.
How much energy will it store?
720 megawatt-hours, which is enough to power over 95,000 homes for a day.
What is the project timeline?
Planning was approved in 2024, construction started in 2025, with completion and commissioning expected in mid-2027.
Will the construction affect the local area?
Elements Green and Mitie are adhering to planning control requirements such as construction traffic management plans, aimed at minimising disruption with managed access and working hours.
What are the working hours?
8am–6pm, Monday–Friday and 8am to 2pm on Saturdays. The approved Construction Traffic Management Plan (CTMP) restricts HGV deliveries between 9am and 4pm Monday to Friday, and 8am to 2pm on Saturdays, avoiding peak traffic periods (8–9am and 5–6pm).
Who do I contact with concerns?
Use the contact section on this website to reach our Community Relations Team or Project Manager.
Complaints & contact
If you’ve experienced disruption (parking, noise, dust, etc.), please contact MITIE who aim to respond to all issues within 3 working days.
Challenges, complaints, and our commitment to getting it right
We want to be clear with our community: since early works began at the Staythorpe BESS site, we’ve faced several important challenges — and local residents have rightly raised concerns. We take these concerns extremely seriously.
Construction vehicles using unauthorised or restricted routes
What We’ve Done:
Reinforced delivery hour restrictions, including refusing early arrivals
Deliveries arriving before permitted hours
What We’ve Done:
Reinforced delivery hour restrictions, including refusing early arrivals
Dust, limited signage, and traffic management concerns
What We’ve Done:
Reinforced delivery hour restrictions, including refusing early arrivals
Our commitment to you
We want to builds trust, provide clarity, and create lasting value for the local community. That means:
Owning mistakes when they happen
Taking swift, visible action to fix them
Learning from feedback
We are determined to set a new standard for how major infrastructure is delivered in partnership with communities.
Schedule
Upcoming events
Events in September 2026
MonMonday
TueTuesday
WedWednesday
ThuThursday
FriFriday
SatSaturday
SunSunday
3131 August 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
11 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
22 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
33 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
44 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
55 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
66 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
77 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
88 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
99 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
1010 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
1111 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
1212 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
1313 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
1414 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
1515 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
1616 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
1717 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
1818 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
1919 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
2020 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
2121 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
2222 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
2323 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
2424 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
2525 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
2626 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
2727 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
2828 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
2929 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
3030 September 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
11 October 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
22 October 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
33 October 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
44 October 2026●(1 event)
All Day 8 May 2026 – 8 November 2026
As the on-site access between the two fields crosses the existing footpath, it is necessary to close FP1 for health and safety reasons. The permissive path will be available for public use during this time to maintain access and reduce disruption to residents.
The closure dates are will be between the 6th May and 8th November 2026.
These measures are in place to prevent and mitigate any risk of accidents during the construction works.
We apologise for any inconvenience caused and thank you for your understanding.
Updates
Subscribe to our Staythorpe BESS CRP newsletter
By submitting this form, you acknowledge that Elements Green may share your personal data with trusted agencies involved in supporting our community project. Your data will only be used for the purposes of managing and facilitating the project, and will not be shared with any third parties outside of this context.
We are committed to handling your personal information in accordance with GDPR and our Privacy Policy: www.elementsgreen/privacy-policy, ensuring it is securely stored and used responsibly.
If you wish to be removed from the mailing list contact: Staythorpe-BESS@elementsgreen.com